The Electricity Commission issued its draft decision to turn down Transpower's grid upgrade proposal to construct a 400kV line linking Whakamaru and Otahuhu by 2010 on 27 April 2006.
In this note, we examine the reasons behind the Commission's draft decision and set out the future timetable for consultation. In summary:
Transpower Proposal:
To construct a new 400kV double circuit line between Whakamaru and Otahuhu.
Electricity Commission Draft Decision:
Unanimous decision not to approve the proposal (draft decision only).
Rationale for Commission's decision:
The proposal reflects good industry practice in meeting the grid reliability standards; and
Transpower has complied with the processes set out in the Rules; but
the proposal does not meet the requirements of the grid investment test, as it does not maximise the expected net market benefit or minimise the expected net market costs when compared with a number of alternative projects.
Next steps:
A designated transmission customer, an authorised representative of parties substantially affected by the grid upgrade proposal or Transpower may, by 11 May 2006, request the Commission to hold a public conference.
The Commission plans to hold hearings in Manukau and Hamilton on 1 and 2 June for people to make oral submissions.
The Commission welcomes submissions from any person. Written submissions must be made to the Commission by 9 June 2006.
If requested, the Commission plans to hold a public conference in Wellington on 6 and 7 July.
The Commission intends to release its final decision in late July.
The Commission set out at the end of its draft decision a number of questions that it invites responses on.
Transpower proposed the construction of a new 400kV double circuit line between Whakamaru and Otahuhu. This construction was proposed as the first step in accomplishing Transpower's long-term strategic vision for 400kV to replace 220kV as the core grid transmission voltage.
Transpower submitted that the proposal is necessary to avoid an increase in risk to security of supply in the Auckland and Northland region at times of peak loading from 2010 and because:
Transpower's economic analysis resulted in the following conclusions (as summarised by the Commission):
Transpower's proposal to construct the 400kV line is an "investment proposal", which was part of a grid upgrade plan submitted to the Commission for approval.
If the Commission approves the investment proposal, this allows Transpower to recover the approved costs of that investment from designated transmission customers in accordance with the transmission pricing methodology set out in section IV of Part F of the Electricity Governance Rules 2003 (Rules).
The Commission is required to consider and assess Transpower's proposal in accordance with the processes and considerations set out in section III of Part F of the Rules. In particular, rule 13.4 provides that, in order to be able to approve the proposal, the Commission must be satisfied that the proposed investment:
Compared to Transpower's proposal, all the alternative projects involve intermediate investments that make more major investment unnecessary for a number of years.
The Commission noted in its briefing on 27 April 2006 that such intermediate investments are not "band aids" but are good electricity practice, supported by international experience.
Transpower's economic analysis of the alternatives to its proposal was largely limited to a comparison of development plans for the entire North Island at the 220kV and 400kV voltage levels, and delay to the proposal through use of diesel peaking plant. Many of the modelled projects presented by Transpower were independent of transmission into Auckland. Even if 400kV were chosen over 220kV for a national transmission development plan, 400kV transmission from Whakamaru to Otahuhu may not necessarily need to be part of that greater plan.
The Commission considered that Transpower has not adequately analysed the credible alternative project consisting of a new 220kV line into Auckland, and has only applied the grid investment test to one alternative project, namely a diesel peaking plant.
|
Proposal |
2010 NPV cost |
|
400kV in 2010 |
775 |
|
400kV in 2017 |
495 |
|
220kV in 2017 |
400 |
|
HVDC in 2017 |
493 |
|
400kV in 2021 |
607 |
In analysing Transpower's proposal against the three criteria, namely whether the proposal reflects good electricity industry practice, complies with the processes set out in the Rules and meets the grid investment test, the Commission considered that:
The Commission's draft decision is not to approve the Proposal.
Commissioner David Close prepared a separate statement that was attached to the end of the Commission's draft decision as Appendix 3, in which the Commissioner stated that he voted with the other Commissioners to decline approval of Transpower's proposal because it did not meet the requirements of the grid investment test when compared with the alternative transmission investment streams.
However, he stated that he has strong reservations about the way in which the grid investment test itself has been developed and applied. The Commissioner's view is that in developing and refining the test attention has been diverted from some of the objectives of the grid investment test (such as promoting certainty for investment) and from the prime purpose of the investment rules, which is to facilitate Transpower's ability to develop and implement long-term plans for investment in the grid.
In addition, the Commissioner considered that the process of identifying alternatives to Transpower's proposal has led to evaluating Transpower's proposal solely as a Whakamaru-Otahuhu transmission upgrade instead of the first stage of a longer term plan for a higher voltage over the North Island core grid.
This approach does not have sufficient regard to the "prudence and foresight" which is emphasised in the Commission's definition of good electricity industry practice.
The main differences between Transpower's approach and the Commission's approach that led the Commission to conclude that the proposal did not meet the grid investment test are as follows:
According to newspaper reports (The Dominion Post, 28 April 2006) Transpower does not support the grid investment test developed by the Commission and did not "comprehend" it, which means that it cannot consider potential amendments to the proposal. In addition, Transpower stated that its proposal would provide more secure supply than alternatives, and the more the investment was delayed the more risk and the more intermediate projects will be needed. Transpower considers that the Commission's alternative proposals require median load and a whole range of projects being delivered in time and in sequence.
In conjunction with submissions on Transpower's proposal and the draft decision, the Commission also seeks views on the value in progressing at this stage a transmission corridor that would accommodate a range of technologies. Establishing such a corridor would provide greater certainty to landowners and to Transpower in its grid planning function.
The Commission will also be considering whether changes to legislation may be necessary to allow Transpower to progress the transmission corridor. At its briefing on its draft decision the Commission commented that land issues were becoming increasingly more important for transmission and that if issues between landowners and Transpower are not resolved soon, there will be a crisis as Transpower faces difficulties in accessing land to maintain the transmission lines.
Capital Costs of Transpower's Proposal and Alternative Projects (in $m 2010)
|
Year of investment |
400kV in 2010 |
400kV in 2017 |
220kV in 2017 |
HVDC in 2017 |
400 kV in 2021 |
|
2010 |
709 |
63 |
63 |
63 |
296 |
|
2016 |
0 |
32 |
32 |
32 |
32 |
|
2017 |
73 |
762 |
479 |
553 |
0 |
|
2018 |
0 |
0 |
0 |
0 |
32 |
|
2020 |
32 |
0 |
0 |
0 |
32 |
|
2021 |
0 |
0 |
0 |
331 |
769 |
|
2022 |
32 |
0 |
60 |
0 |
0 |
|
2023 |
0 |
0 |
97 |
0 |
0 |
|
2024 |
41 |
67 |
0 |
0 |
0 |
|
2025 |
0 |
0 |
0 |
64 |
1 |
|
2026 |
4 |
0 |
127 |
42 |
0 |
|
NPV (as at 2010) |
802 |
585 |
493 |
624 |
718 |
NPV Summary of Modelled Proposal and Alternative Projects ($m 2010)
|
|
400kV in 2010 |
400kV in 2017 |
220kV in 2017 |
HVDC in 2017 |
400kV in 2021 |
|
Mean PV capital cost (A) |
775 |
495 |
400 |
493 |
607 |
|
Mean PV O&M cost (B) |
15 |
6 |
3 |
10 |
3 |
|
Mean PV net loss cost (C) |
0 |
76 |
118 |
74 |
109 |
|
Mean PV net reliability benefits (D) |
0 |
5 |
15 |
13 |
15 |
|
Mean PV terminal benefit (E) |
31 |
30 |
6 |
15 |
45 |
|
Mean PV excess capacity benefit (F) |
5 |
0 |
0 |
0 |
0 |
|
Mean PV total cost (A+B+C-D-E-F) |
754 |
541 |
499 |
549 |
658 |
This publication is necessarily brief and general in nature. You should seek professional advice before taking any action in relation to the matters dealt with in this publication.