Safeguarding electricity supply
Thursday 29 May 2003
By the Electricity Group, Bell
Gully
On 20 May, the Government announced new measures to safeguard future
electricity supplies, including the establishment of a new Electricity
Commission. We have summarised the key points of this announcement below.
Overview- establishment
- An Electricity Commission will be formed and directed to ensure
that the industry operates to a "1 in 60" dry-year security
standard.
- The Commission is expected to be a statutory commission with the
powers of an Electricity Governance Board as outlined in the Electricity
Amendment Act 2001.
- Seven commissioners are due to be appointed by the end of August
2003.
- A legislative package is due to be introduced in August or September.
- The Commission will contract with generators for the provision
of dry-year reserve generation capacity and fuel.
- The Commission will receive the spot price when the ring-fenced
capacity is dispatched by the system operator.
- The Commission's net costs will be recovered through a levy on
market participants - estimated at well under half a cent per unit of
electricity.
- The Commission will be given an additional "toolbox"
of powers to deliver on its security objective.
Contracts for security reserve
- The Commission will contract by tender for a quantity of new and/or
existing generation as a "security reserve" to be set aside
or ring-fenced from the market. The Commission will determine the prices
and quantities offered to the market by this ring-fenced capacity.
- The Commission will be expected to hold a mixed portfolio with
capacity at different locations and with different fuel types in order
to manage the impact of contingencies such as disruptions to fuel supplies.
- Reserve generation is expected to comprise new plant with relatively
low capital costs, plus heavily depreciated old plant.
- The necessary portfolio of reserve generation is expected to be
built up within about three years.
- Payments from the Commission under the ring-fencing contracts will
cover the capital and maintenance costs of the plant and the cost of fuel.
- Competition in generation will be encouraged by a legislative amendment
enabling owners of electricity lines businesses to invest in reserve generation
without limit as to quantity.
- The competitive bidding process is expected to ensure that the
owners of ring-fenced reserve capacity do not earn profits above or below
their risk-adjusted cost of capital.
- Some of the Commission's contracts for reserve capacity may be
of a sufficiently long-term duration to be capable of backing the construction
of new "hydro-firming" plant. Contracts involving existing generation
capacity are likely to be shorter but may still cover multiple years.
- Contracts for reserve capacity are expected to include provision
for regular audits by the Commission concerning plant and fuel availability,
and severe penalties for breaches of contract.
Dispatch of reserve capacity
- Reserve capacity is to be sold on the spot market.
- There are some important considerations relating to the Commission's
offer price into the spot market for reserve generation. If the generation
is offered at too low a price, this may reduce the commercial incentives
to build new high load-factor plant or invest in demand-side management,
as an effective cap would be established at a low price. However, if the
reserve is offered into the market at a price significantly above its
short run marginal cost, the reserve capacity will be used less frequently
(even though it may be efficient to operate it more frequently), and spot
prices will be higher than necessary.
- A further option may be to offer the generation in tranches at
different prices. An initial tranche of the ring-fenced reserve generation
might operate relatively frequently (for example, when inflows were below
mean and/or lake levels were relatively low for that time of year). Subsequent
units of ring-fenced generation would have a progressively lower load
factor. The last units of ring-fenced generation would run very rarely.
- The Commission might also have discretion as to whether to maintain
a standing offer price into the spot market, or whether it may vary the
offer price on the basis of its assessment of the risks of supply shortages.
- The ring-fenced capacity will be fully committed, providing an
effective cap on the spot price to the whole market (with the costs met
by a levy on all market participants).
Net cost recovery- consumer levies
- The Commission will have the power to recover the cost of reserve
generation in the manner it judges to be most efficient, for example through
a levy.
The "tool box"
- The Commission will have additional powers in its "toolbox"
to deliver security of supply. These powers will be available as a backstop
to help the Commission ensure that the market operates as efficiently
as possible.
- The toolbox includes power to set minimum requirements on generators
to hold dry-year reserves and long-term financial contracts. The Commission
will also be able to set minimum requirements on retailers and major users
to hold long-term financial contracts and/or maintain programmes for reducing
demand when spot prices rise.
Other powers and functions
- The Commission will be empowered to require generators to offer
long-term electricity hedge contracts into the market, for a nominated
proportion of their reliable capacity, if it decides this is necessary
to safeguard against under-investment in ordinary generation.
- The Commission will pick up routine governance functions from existing
industry bodies. Commencement rules for the Commission will be based on
the rulebook developed by the recent industry processes, suitably amended
to take account of the establishment and decision-making role of the Commission.
Draft commencement rules will be put out for a brief period of consultation
by the end of June.
- The Commission will be responsible for improved modelling and forecasting
of future electricity supply and demand.
- It will also have new powers to require disclosure of information
including coal stockpiles and more timely data on gas discoveries and
reserves. It will require publication of amalgamated figures for the total
quantity and price of all hedge contracts.
- It will also be charged with improving the industry's ability to
manage ripple control for water heating.
- Urgently address transmission investment and pricing. The national
grid is in a mostly satisfactory shape, but there is no agreement in the
industry about who is responsible for making decisions about new transmission
investments and who should pay for them. This means that when new transmission
investment is needed Transpower has no certainty it can get paid for it,
which means Transpower is under-investing in the grid, or soon will be.
If you would like to know more about the new Commission and how it
may affect your organisation, please contact the Bell Gully Electricity
group.
Click here
to read the Government announcement and discussion paper.
Disclaimer: Bell Gully provides these links to other websites to help
you find related information. Bell Gully is not responsible for their
content, accuracy, completeness or reliability.
Disclaimer
This publication is necessarily brief and general in nature. You should seek professional advice before taking any action in relation to the matters dealt with in this publication.